Within the framework of the public-private partnership (PPP) model, income guarantees, which impose a significant burden on the public budget, come to the fore frequently. It can be expected that discussions on this issue will intensify as we move toward the election.
PPP is a widely used system in the world. The World Bank’s definition is as follows: “A long-term contract between a private party and a government entity, for providing a public asset or service, in which the private party bears significant risk and management responsibility and remuneration is linked to performance” (World Bank, page 14).
For those who want to learn more about the subject in detail, I recommend the December 2021 TEPAV report written by Çoşkun Cangöz, Uğur Emek, and Nurhan Uygunranoğlu Karaca (You can reach from here).
Why is this highly technical issue so hot?
The answer is clear, although it is not the same in every project, there are such guarantees that come to the fore that one cannot help but get nettled. For example, guarantees are given as if 1.000 passengers would come to a place where 100 passengers arrive. A much more detailed analysis of this subject can be found in the column of Uğur Emek, one of the authors of the above-mentioned report.
If a healthy economy program is to be designed and implemented after the 2023 election, the income guarantees given to these projects should be reconsidered. The legal part of the matter is essential; nonetheless, I have nothing to say in this regard. If the burden on the budget from these guarantees can be alleviated in a way that does not cause legal problems, it is possible to create additional room for maneuvering in fiscal policy.
Having fiscal room is vital to combat poverty brought on by high inflation.
Let me recount an anecdote from years ago. If I am not mistaken, the first version of this system was the “build-operate-transfer” system, put into use during Turgut Özal’s term in the mid-1980s. I took part in the feasibility study of a project developed within the framework of that system. The late Kemal Kurdaş was the head of the holding which undertook the implementation of the project.
In the holding, we were two people responsible for investments under him.
A company affiliated with the holding outsourced a preliminary feasibility report to an engineering company. On behalf of the holding, I was dealing with the project: I was in a team of three people who would finalize the feasibility project. The other two were the head of a company affiliated with the holding and were responsible for the engineering part due to their significant experience in energy projects in the government. My responsibility was the project’s economic feasibility.
The project was about establishing a hydroelectric power plant and selling the generated electricity to the state. According to the preliminary report, the project considered very profitable.
Nevertheless, there was one detail not emphasized much in the preliminary project. Electricity would be produced by a hydroelectric power station without a dam. In this case, the more water would flow from the river, the more energy would be produced. Therefore, the flow rate of the water was one of the significant factors determining the feasibility.
Each river in Turkey has daily water measurements dating back to the first years of the Republic. After digging a bit, we saw that there were such dry periods that the amount of water flowing through the river decreased extremely for four years in a row.
Therefore, with the help of a simple scenario analysis, it was possible to examine the profitability of the project in case such a period coincided with the completion of the investment period and the commissioning of the power plant.
Under this scenario, with the unit energy sales prices accepted in the preliminary project report, the project was almost deemed infeasible; there was a significant risk. I recall that, in the negotiations with the Ministry of Energy, the project was deadlocked on what the unit energy price would be.
First of all, it should be noted that the PPP system is beneficial to the economy if used properly. After all, the state does not have the means to reach everywhere; The PPP system has the potential to remedy this constraint.
The keyword here, of course, is “healthy use”. It is clear from the above discussion that income guarantees are essential for the PPP model because it deeply affects the feasibility of the project.
Well, is it possible to reconsider the income guarantees of the projects implemented within the framework of the PPP model in the upcoming period? Technically, the answer is “of course”. So what kind of framework can be thought of?
There are several criteria to evaluate any investment from a company’s perspective.
One of the most significant ones is the “internal rate of return”.
Let us summarize: Consider the following periods; the period of investment, and the period when the facility is put into operation and “production” is made until the end of its life. There are cash outflows during the investment period and net cash inflows during the active operation period. (Net cash inflows may also be negative in some active operation years.)
Let us say 1 billion liras were spent on investment in the first year, and an after-tax profit of 500 million liras were made in the fifth year.
1 billion liras spent in the first year and 500 million liras of profit in the fifth year are not equivalent: One is in the first year and the other in the fifth year. To express them in the same unit, future cash outflows and inflows are discounted; brought to the present.
The internal rate of return is a rate that equates to the present value of net cash inflows and outflows. For the entrepreneur, it refers to the expected rate of return to be obtained from the project.
In the report that I mentioned at the beginning of the article, it is stated that in the projects developed in Turkey within the framework of the PPP model these calculations are made by the entrepreneur. Besides, for the project to be financed, these reports must be given to the financiers.
From this perspective, it can be assessed whether any of the existing public-private partnership projects operate with an “excessive” rate of return.
The critical variables are:
If the recalculated rate of return is reasonable, then it is possible to sit at the bargaining table.
Of course, other evaluation methods can also be used. The critical thing is that it is possible to re-evaluate the projects and consequently the income guarantees. For some projects this may not be effortless, however, it should be clear that it is a doable job.
On October 30th, the European Commission published its annual report assessing the candidate countries' progress…
Greek Cypriot Nikos Christodoulides’ recent meeting with U.S. President Joe Biden at the White House…
The opposition Republican People's Party (CHP) mayor of Istanbul's Esenyurt district, Prof. Ahmet Özer, was…
As Türkiye celebrates the 101’st anniversary of its Republic, the definition of a “democratic, social…
Terrorism is one of the most sensitive issues facing the country, yet here we are…
Despite the considerable excitement surrounding Turkey's potential BRICS membership, the outcome has yielded little of…